Land in Rock garden, Yapral

Soil Testing

Level station survey

Borewell digging

Plain concrete cement (m10, 140+90)

Column placement (tata steel fe 500 d)

Anti-termite treatment - 1

Concrete for footings M25 (250+90)

Column laying M25 (250+90)

Anti-termite treatment Level 2 at Plinth level

Slab - 1 construction

Birla Aerocon Blocks marking

Sil level construction (Bond beam & Doors)

Anti-Termite Treatment level 3 in the Flats